September 2018

Contract Award

The City awards the main construction contract to Tritech Group
September 2018 → November 2020

Phase 1 - Plant construction and lagoon upgrades

September 2019 → February 2020

Phase 2 - Outfall and diffuser construction

This work is being carried out during a Fisheries window to ensure the health and well-being of fish and fish habitat.
October 2020

Phase 3 - Commissioning

March → June 2021

Phase 4 - Lagoon decommissioning and habitat restoration

Consultation and engineering is required for this aspect of the project. A start date for actual restoration is to be determined.
June 15 → July 05 2020

LWMP Combined Stage 2/3 Community Engagement

Formation of the Plan Monitoring Committee, Public Consultation and First Nations Engagement 

July 27 2020

Council directed staff to advance the Stage 2/3 Liquid Waste Management Plan to B.C. Ministry of Environment and Climate Change Strategy